Case Study 3

 

Once in France the machines were unloaded into the factory via a loading bay.

As the machines were going in a pit, a ramp was constructed for two purposes:

  1. To allow us to install the large mill with our machine skates.
  2. To allow us to drive the fork lift into the pit to install the mixer.

The mezzanine floor was shortened and the mixer was installed and levelled. The mill was installed once the mixer was in. Our engineers then re-connected the interconnections and site services.

With the machinery ready for testing we performed the following tests.

  • Phase rotation
  • Voltage
  • Temperature
  • Flow of water

Once these checks had been completed the machines were handed over to the customer.

 

<< Page 1