Once at the new site the lines where installed in parallel to their existing foot print.
Due to the voltage and frequency difference between the USA and the UK a 50HZ conversion was under taken of both lines this entailed changing most motors and transformers.
The lines then had their final checks:
Once all of these tasks had been undertaken successfully the line had a 5 minute shakedown, to check rotation on the motors and also to see whether any of the components had come loose in transit.
After the shakedown a full 1 hour dry run was undertaken, monitoring the lines for:
After the 1 hour dry run was completed the line was handed over to the customer.